A boiler room delivered with the progress report matching the hours

Industrial plant contractor · 22 people · Lombardy

Refit of a boiler room planned at 1,140 hours. The piping item was slipping: it surfaced in week three instead of at commissioning.

when the deviation surfaced
Week 3
planned hours read from the report
1,140 h
hours counted twice
0
Diagram of an industrial piping line with fittings highlighted.

Where they started

The progress report was written by hand before every client meeting, from signed sheets and the site manager’s memory. The margin was known only once the job was closed.

What changed

The contractual report PDF was uploaded on day one: six items with estimated hours, from dismantling to start-up. The crew kept signing the weekly sheet, photographed every Friday.

By week three, steam and condensate piping had used 69% of its hours against 55% declared progress. The owner raised it with the client before the meeting, not during it.

The outcome

A variation agreed in time instead of a dispute at the end, and a margin visible every week instead of at final accounts.

I used to write the progress report on Sunday night. Now I open it on Friday and already know which item I need to explain to the client.

Paolo FerrettiOwner, industrial plant contractor, 22 people